December Deadline Doubtful as New Facts Emerge on Port Harcourt Refinery

December Deadline Doubtful as New Facts Emerge on Port Harcourt Refinery

  • The managing director of the Port Harcourt Refinery, Ibrahim Onoja, has said the work on the project is progressing speedily
  • He said the refinery is about 75% complete and would be delivered on schedule this month
  • Onoja stated that the essential parts of the refinery have been changed and that workers run day and night shifts to meet the deadline

Pascal Oparada has over a decade of experience covering Tech, Energy, Stocks, Investments, and Economy.

The Managing Director of the Port Harcourt refinery project, Ibrahim Onoja, has said that over 75% of the refinery has been completed.

Onoja disclosed this in a report by the Nigerian National Petroleum Company Limited (NNPCL) to show the level of progress at the refinery.

Ibrahim Onoja, PH Refinery
Work ongoing at the Port Harcourt Refinery Credit: NNPCL
Source: Getty Images

Major parts of the refinery replaced

He said workers now run day and night shifts and have completed most of the procurement, with 98% delivered.

Read also

Nigerian refineries attract investment from one of world’s largest oil field services companies

PAY ATTENTION: Сheck out news that is picked exactly for YOU ➡️ find the “Recommended for you” block on the home page and enjoy!

He said:

“We have refineries over a hundred years old; the essential static equipment, the metallic part you see, remains fundamentally the same.
“Upgrades happen over the years. Yes, the Port Harcourt refinery was built in 1965, but as time went on, the instrumentation equipment was upgraded.”

The refinery, built in 1965, is undergoing an extensive overhaul and change of essential parts.

Reports say that the NNPC report said that the instrumentation and control unit is undergoing overhaul, and the rotating equipment comprising the pumps and compressors have been upgraded and are all in place.

According to the report, the electrical systems, which include substations, transformers, switchgear, cables, and panels, are brand new.

The report highlighted that electrical systems, which include substations, transformers, switchgear, cables, and panels, are all brand new.

Read also

Newly launched Nigerian refinery announces date for implementation of phase 2

The refinery would be completed on schedule

Onojo stated that the refinery repairs have been ongoing since April 2021, saying that 3000 workers work on the project, recording 8.3 million person-hours with zero lost time to injuries.

He said that the December deadline given by President Bola Tinubu and the Minister of Petroleum Resources (Oil) Heineken Lokpobiri would be met.

The Port Harcourt refinery boss revealed that operations would begin this month with the production of petrol, liquified petroleum gas (LPG), Kerosene, low and high-pour fuel oil, and diesel.

The NNPC Managing Director, Mele Kyari, said last month that the refinery will be ready by December.

He said the Warri and Kaduna refineries will commence operation in 2024.

“I Can Confirm”: Nigerian government refinery to begin operation in December

Legit.ng reported that Mele KyarI, the Group Chief Executive Officer of the Nigerian National Petroleum Company Limited, has assured that the Port Harcourt refinery will take off in December 2023.

Read also

No more shortages: FG launches new metre factory in Nigeria

He gave this assurance while meeting with the Speaker of the House of Representatives, Tajudeen Abbas, on Thursday, November 23.

The Port Harcourt refinery has undergone a $1.5 billion upgrade after Italy's Tecnimont was awarded the contract to carry out the work in 2021.

Source: Legit.ng

Authors:
Pascal Oparada avatar

Pascal Oparada (Business editor) Pascal Oparada is a Mass Communications Graduate from Yaba College of Technology with over 10 years of experience in journalism. He has worked in reputable media organizations such as Daily Independent, TheNiche newspaper, and the Nigerian Xpress. He is a 2018 PwC Media Excellence Award winner. Email:pascal.oparada@corp.legit.ng