Buhari commissions power transmission sub-station in Yobe

Buhari commissions power transmission sub-station in Yobe

- A new 330/132/33KV transmission substation in Damaturu, Yobe state, was commissioned by President Muhammadu Buhari

- The management of Transmission Company of Nigeria was commended for the timely and cost effective completion of the project

- The minister of state for power, works and housing, Suleiman Zarma, represented President Buhari at the commissioning

President Muhammadu Buhari on Wednesday, February 13, commissioned a new 330/132/33KV transmission substation in Damaturu, Yobe state.

The News Agency of Nigeria (NAN) reports that Buhari was represented by the minister of state for power, works and housing, Suleiman Zarma.

Legit.ng gathers that he said the event marked another milestone in ‘our collective resolve’ to take the nation’s power sector to the next level of efficacy and relevance.

READ ALSO: NAIJ.com upgrades to Legit.ng: a letter from our Editor-in-Chief Bayo Olupohunda

He said: “It is also an indication that a government’s owned company such as Transmission Company of Nigeria (TCN) is taking giant stride in expanding its capacity to make electricity more readily available in the country.’’

He added that after all installation had been done, the 150MVA, 330/132/33KV transformer, 75MVAR reactor were energised on September 13, 2018, while the 60MVA, 120/33KV transformer was put to service on October 3, 2018.

Buhari said: “Thereby enabling supply access to the three outgoing Feeders: Buni Yadi feeder 1, Damaturu feeder 2 and Babban Gida feeder 3.

“The major towns to benefit from the supply include Ganjarma, Gaidam, Dapchi, Yadi and Damaturu Township picking cumulative power of up to 13.8MW presently.

The president commended the management of TCN for the timely and cost effective completion of the project.

He said: “Even though the project started in 2006 and was delayed, I am happy to commend the initiatives of the TCN new management who have adopted the regional empowerment and in-house project completion strategy that make this project realisable.

“I therefore congratulate the management and engineers of TCN for completing and energising this substation at a minimal cost.”

The Yobe state governor, Alhaji Ibrahim Gaidam, represented by his deputy Abubakar Aliyu, commended the federal government for its efforts towards improving the power sector.

He added: “Thanks to the efforts of Federal Government under the visionary leadership of President Buhari who improved power generation from less than 3000MW to over 7000MW.”

PAY ATTENTION: Install our latest app for Android, read best news on Nigeria’s #1 news app

He urged the minister and the managing director of TCN to sustain the tempo for the betterment of the country.

Meanwhile, Legit.ng previously reported that the 80MVA Yauri transmission substation in Kebbi state would be commissioned this week by the minister of power, works and housing, Babatunde Raji Fashola, after 11 years of abandonment.

The transmission substation, which was abandoned by contractors after it was started in December 2007, was completed by the in-house engineers of the Transmission Company of Nigeria (TCN).